Measuring Concrete: Bags or Ready-Mix?
Record the footprint and the specified depth for each part of your project. Then use the volume to compare bags of premix with a separate ready-mix quote.
Back to guidesEnter your dimensions in the Concrete Calculator
How to measure
Use a tape for short straight edges or a measuring wheel for longer boundaries. Label each section on a sketch and write down length, width and units. Recheck readings before entering them.
Record the measured or specified depth at several points. Use separate parts where depth changes, with one depth for each part. Replace the calculator’s starting depth with your project’s value.
Record long edges in metres and depth in centimetres. Divide centimetres by 100 to write them as metres: 125 cm is 1.25 m. Keep your original readings. If you round a measurement, round it up.
Count each volume once
A rectangular strip uses length × width × depth. Where two strips cross, split the sketch so their shared corner is counted once. A circle uses the full diameter or the radius from centre to edge, then depth.
A circular footprint represents a solid filled cylinder. If a post or another object occupies part of it, establish the net area to be filled first. Known Area lets you enter that separately measured area with a uniform depth.
Keep each depth and product clear
The calculator adds the part volumes before applying allowance and rounding to whole bags. Allowance is extra volume you choose to order.
Use one premix product and bag yield for a project. Estimate different products separately so each has its own yield and quote.
Check how much finished concrete a bag makes
Bag weight is dry weight. Finished yield is the volume of concrete one bag makes. The calculator’s weight method uses an approximate 0.5 litres per kilogram of dry premix; it is not a product’s stated yield and applies to premix, not cement alone.
When the product gives a finished yield, choose Volume per bag under the advanced option. Enter that volume in litres. This replaces the weight estimate.
Get a separate ready-mix quote
For a quote per m³, select that price unit. Enter the new rate after switching from bag pricing. A bulk quote uses order volume, so it needs no bag yield.
Ask about minimum orders, selling increments and the complete delivery charge. The displayed volume is the calculated amount before any supplier minimum or increment.
Worked example: compare bag methods and a bulk quote
Metric example: use one Rectangle part. Compare a 20 kg bag using the approximate weight method with a different bag whose label states a finished yield of 17 L. Allowance and example prices are chosen inputs; enter price numbers only.
Enter these inputs
- Rectangle footprint
- 4 m × 4 m
- Thickness / depth
- 12.5 cm
- First scenario
- 20 kg bag weight; 0% allowance; no price
- Second scenario
- Volume per bag: 17 L; $8 per bag; 0% allowance
- Allowance comparison
- 10% with the same entered yield and bag price
- Independent bulk comparison
- Reset allowance to 0%; $100 per m³
Follow the calculation
- 4 × 4 = 16 m². Multiply by 12.5 cm, or 0.125 m: the volume is 2 m³.
- The approximate weight method uses 0.5 L/kg. A 20 kg bag gives about 10 L, so 2 m³ needs an estimated 200 bags. Use the product’s stated yield for the next comparison.
- Select the advanced Volume per bag option and enter 17 L. 2 m³ is 2000 L; divide by 17 and round upward to 118 whole bags. At $8 per bag, material cost is $944. The entered yield replaces the weight estimate.
- With the chosen 10% allowance, order volume becomes 2.2 m³. At 17 L per bag, round up once for the project to 130 bags; material cost is $1040.
- For a separate bulk comparison, reset allowance to zero and select price per m³. At $100/m³, 2 × 100 = $200. Bag details are not needed for this bulk cost.
Read the purchasing result
- Base volume
- 2 m³
- Generic weight estimate
- 200 bags
- Entered-yield order / cost
- 118 bags / $944
- Entered yield with allowance / cost
- 130 bags / $1040
- Separate zero-allowance bulk quote
- $200
How to measure
Use a tape for short straight edges or a measuring wheel for longer boundaries. Label each section on a sketch and write down length, width and units. Recheck readings before entering them.
Record the measured or specified depth at several points. Use separate parts where depth changes, with one depth for each part. Replace the calculator’s starting depth with your project’s value.
For decimal feet, divide inches by 12 and add the feet: 9 ft 6 in is 9.5 ft. Depth can be entered directly in inches. Keep your original readings. If you round a measurement, round it up.
Count each volume once
A rectangular strip uses length × width × depth. Where two strips cross, split the sketch so their shared corner is counted once. A circle uses the full diameter or the radius from centre to edge, then depth.
A circular footprint represents a solid filled cylinder. If a post or another object occupies part of it, establish the net area to be filled first. Known Area lets you enter that separately measured area with a uniform depth.
Keep each depth and product clear
The calculator adds the part volumes before applying allowance and rounding to whole bags. Allowance is extra volume you choose to order.
Use one premix product and bag yield for a project. Estimate different products separately so each has its own yield and quote.
Check how much finished concrete a bag makes
Bag weight is dry weight. Finished yield is the volume of concrete one bag makes. The weight method is an approximate estimate for dry premix, not a product’s stated yield. Use the actual product yield when it is available.
Choose Volume per bag under the advanced option, select ft³ and enter the stated yield. This replaces the weight estimate.
Get a separate ready-mix quote
For a quote per yd³, select that price unit. Enter the new rate after switching from bag pricing. A bulk quote uses order volume, so it needs no bag yield.
Ask about minimum orders, selling increments and the complete delivery charge. The displayed volume is the calculated amount before any supplier minimum or increment.
Imperial example: bags and a ready-mix quote
Use feet and inches for a Rectangle part. The entered yield is 0.6 ft³ per bag. The 10% allowance and example prices are chosen examples; enter price numbers only.
Enter these inputs
- Rectangle
- 9 ft × 6 ft; 4 in depth
- Bag yield
- Volume per bag: 0.6 ft³; first use 0% allowance
- Bag order
- Then use 10% allowance; $8 per bag
- Separate bulk quote
- Reset allowance to 0%; $150 per yd³
Follow the calculation
- 9 × 6 = 54 ft². At 4 in, or one-third of a foot, the volume is 18 ft³. In cubic yards it is 18 ÷ 27, displayed as 0.67 yd³.
- Choose Volume per bag and ft³, then enter 0.6. With zero allowance, 18 ÷ 0.6 = 30 bags.
- Add the chosen 10% allowance: 18 × 1.1 = 19.8 ft³, displayed as 0.73 yd³. Divide the unrounded volume by 0.6: 33 whole bags. At $8 each, cost is $264.
- For a separate ready-mix quote, reset allowance to zero, select per yd³ and enter 150. Use the full 18 ÷ 27 yd³, rather than the rounded display: the material cost is $100.
Read the purchasing result
- Base volume
- 18 ft³ / 0.67 yd³
- Bags without allowance
- 30 bags
- With allowance
- 19.8 ft³ / 0.73 yd³
- Bag order / material cost
- 33 bags / $264
- Separate bulk material cost
- $100
What this guide does not cover
This guide estimates quantity and material cost. It does not choose depth, mix, strength or reinforcement, provide code or installation advice, or plan delivery and placement. Tax, delivery and fees are outside the calculator total.
Before you order
- Every section counted once with its own depth and units.
- Occupied spaces and changing depths resolved before entry.
- One premix product used; its finished bag yield checked.
- Chosen allowance, quote unit, supplier minimums and extra charges confirmed.